You don't have javascript enabled. Good luck with that.
Pencarian
Dishub Rekayasa Lalu Lintas Jalan Ciledug Raya

Traffic Diversion in Place for Motorists at Jalan Ciledug Raya

The Jakarta Transportation Agency (Dishub) is detouring traffic at Jalan Ciledug Raya, South Jakarta, starting from the instersection of Jalan Seskoal to Cipulir Market.

This work will be executed from May 6 to November 30, 2024

It aims to smoothen the Jacking Channel construction which aims to anticipate flooding on Jalan Ciledug Raya.

"This work will be executed from May 6 to November 30, 2024," expressed Jakarta Dishub Head, Syafrin Liputo, Friday (5/17).

Traffic Diversion at Pakubuwono VI Intersection Efforts to Parse Congestion

Here are the stages of jacking channel work:

a. Pit 8 arriving pit

• From May 6 to July 12, 2024

• The work dimension area is 6x5 meters, there will be narrowing of traffic lanes during the work

b. Pit 9 starting pit

• From May 6 to July 21, 2024

• The work dimension area is 20x5 meters, there will be narrowing of traffic lanes during the work

c. Pit 6 starting pit

• From May 20 to September 22, 2024

• The work dimension area is 30x5.5 meters, there will be an occupancy of the road, traffic will be diverted via a replacement median road separating the road (the area under the corridor 13 overpass)

d. Pit 2 starting pit

• From May 27 to September 8, 2024

• The work dimension area is 30x5.5 meters, there will be an occupancy of the road, traffic will be diverted via a replacement median road separating the road (the area under the corridor 13 overpass)

e. Pit 4 starting pit

• From June 3 to September 22, 2024

• The work dimension area is 26.7x5.4 meters, there will be an occupancy of the road, traffic will be diverted via a replacement median road separating the road (the area under the corridor 13 overpass)

f. Pit 1 arriving pit

• From July 15 to Oktober 20, 2024

• The work dimension area is 26.7x5.4 meters, there will be an occupancy of the road, traffic will be diverted via a replacement median road separating the road (the area under the corridor 13 overpass)

g. Pit 7 arriving pit

• From September 23 to November 10, 2024

• The work dimension area is 15x5 meters, there will be narrowing of traffic lanes during the work

h. Pit 3 arriving pit

• From September 30 to November 17, 2024

• The work dimension area is 15x5 meters, there will be an occupancy of the road, traffic will be diverted via a replacement median road separating the road (the area under the corridor 13 overpass)

i. Pit 5 arriving pit

• From October 21 to November 30, 2024

• The work dimension area is 15x5.4 meters, traffic will be diverted via a replacement median road separating the road (the area under the corridor 13 overpass)

"We hope that road users can adjust to the diversions, obey the traffic signs and instructions from officers and prioritize road safety," he stated.

Linked News
Popular News indeks
  1. Pramono Pushes to Complete Long-Delayed Pluit JLNT by March 2027

    access_time20-11-2026 remove_red_eye697 personDessy Suciati
  2. JAF 2026 Highlights Maritime Heritage and Coastal Architecture

    access_time21-11-2026 remove_red_eye683 personAnita Karyati
  3. Hosted in Sydney, Pramono Discusses Opening Australian Campuses in Jakarta

    access_time25-11-2026 remove_red_eye667 personDessy Suciati
  4. Jakarta Strengthens ASEAN Cooperation on Climate, Transport, and Youth

    access_time20-11-2026 remove_red_eye638 personFolmer
  5. BORJU Markets 200 Local Products

    access_time20-11-2026 remove_red_eye607 personAnita Karyati