Dishub Rekayasa Lalu Lintas Jalan Ciledug Raya

Traffic Diversion in Place for Motorists at Jalan Ciledug Raya

The Jakarta Transportation Agency (Dishub) is detouring traffic at Jalan Ciledug Raya, South Jakarta, starting from the instersection of Jalan Seskoal to Cipulir Market.

This work will be executed from May 6 to November 30, 2024

It aims to smoothen the Jacking Channel construction which aims to anticipate flooding on Jalan Ciledug Raya.

"This work will be executed from May 6 to November 30, 2024," expressed Jakarta Dishub Head, Syafrin Liputo, Friday (5/17).

Traffic Diversion at Pakubuwono VI Intersection Efforts to Parse Congestion

Here are the stages of jacking channel work:

a. Pit 8 arriving pit

• From May 6 to July 12, 2024

• The work dimension area is 6x5 meters, there will be narrowing of traffic lanes during the work

b. Pit 9 starting pit

• From May 6 to July 21, 2024

• The work dimension area is 20x5 meters, there will be narrowing of traffic lanes during the work

c. Pit 6 starting pit

• From May 20 to September 22, 2024

• The work dimension area is 30x5.5 meters, there will be an occupancy of the road, traffic will be diverted via a replacement median road separating the road (the area under the corridor 13 overpass)

d. Pit 2 starting pit

• From May 27 to September 8, 2024

• The work dimension area is 30x5.5 meters, there will be an occupancy of the road, traffic will be diverted via a replacement median road separating the road (the area under the corridor 13 overpass)

e. Pit 4 starting pit

• From June 3 to September 22, 2024

• The work dimension area is 26.7x5.4 meters, there will be an occupancy of the road, traffic will be diverted via a replacement median road separating the road (the area under the corridor 13 overpass)

f. Pit 1 arriving pit

• From July 15 to Oktober 20, 2024

• The work dimension area is 26.7x5.4 meters, there will be an occupancy of the road, traffic will be diverted via a replacement median road separating the road (the area under the corridor 13 overpass)

g. Pit 7 arriving pit

• From September 23 to November 10, 2024

• The work dimension area is 15x5 meters, there will be narrowing of traffic lanes during the work

h. Pit 3 arriving pit

• From September 30 to November 17, 2024

• The work dimension area is 15x5 meters, there will be an occupancy of the road, traffic will be diverted via a replacement median road separating the road (the area under the corridor 13 overpass)

i. Pit 5 arriving pit

• From October 21 to November 30, 2024

• The work dimension area is 15x5.4 meters, traffic will be diverted via a replacement median road separating the road (the area under the corridor 13 overpass)

"We hope that road users can adjust to the diversions, obey the traffic signs and instructions from officers and prioritize road safety," he stated.

Linked News
Popular News indeks
  1. Transjakarta Commits to Accelerating Modal Integration and Fleet Electrification

    access_time31-08-2026 remove_red_eye601 personAldi Geri Lumban Tobing
  2. JITEX 2026: Fostering a Global Trade and Investment Ecosystem

    access_time01-09-2026 remove_red_eye563 personAldi Geri Lumban Tobing
  3. Pramono Confirms Permanent Bridge to Be Built in Tegal Alur

    access_time29-08-2026 remove_red_eye460 personDessy Suciati
  4. Jakarta Fine Arts and Ceramics Museum Hosts Malangan Exhibition

    access_time29-08-2026 remove_red_eye458 personFakhrizal Fakhri
  5. Pramono Emphasizes Importance of Creative Spaces for Children

    access_time03-09-2026 remove_red_eye434 personDessy Suciati